Another update of the schedule.
Today
Early this morning a first test of the DORIS power supplies was performed.
Starting at 10:00hrs the toroid power supply, cabling and magnet was
tested successfully. The magnet was at full field for about 15min.
This afternoon the interlock is set until 18:00hrs in order to continue
the DORIS power supply tests.
Monday
Perform interlock tests. There will be no access until about 17:00hrs.
Crane repair
Tuesday
Close tunnel ceiling
Open detector main frames
Start survey
Wednesday - Thursday
Survey and detector alignment
Friday
Remaining activities
Start beam operation
Best regards,
Uwe
_____________________________________________________
|
| Dr. Uwe Schneekloth
| OLYMPUS
| Deutsches Elektronensynchrotron
| Notkestrasse 85
| D-22603 Hamburg/Germany
| Tel: +49-40-8998 2007 Fax: +49-40-8998 3092
| email: uwe.schneekloth at desy.de
_____________________________________________________
More information about the Olympus
mailing list