<br><font size=2 face="sans-serif">We have recently implemented the PO,
the contract and the sched agreements approval workflows. &nbsp;A problem
is &quot;sometimes&quot; occurring in production where the approval workitem
step receives the terminating event (the approval has been done), but the
workflow doesn't complete. &nbsp;It just stays in process, and stays in
the approvers in-box even though they already did the approval. &nbsp;I
searched OSS and even implemented note 831443 thinking there may be some
type of locking problem happening. &nbsp;I have not been able to re-produce
this in our Dev or QA environment. &nbsp;Also this mainly is happening
with contracts and sched agreements, not PO's. &nbsp;Any ideas?</font>
<br>
<br><font size=2 face="sans-serif">We are on a 4.7 system. &nbsp;Thanks.</font>
<br><font size=2 face="sans-serif"><br>
Tami Elliott</font>
<br><font size=2 face="sans-serif">Eastman Kodak Company<br>
<br>
<br>
</font>