<br><font size=2 face="Arial">He is partially correct. The release strategy it self is looking for the release at the level it was rejected. Therefore, at that time the Requisitioner or someone else has to do something with the requisition (Change it).</font>
<br><font size=2 face="Arial">Now comes the workflow part, unless the requisition is &quot;significantly changed&quot; the Event for ReleaseStep will not be raised.</font>
<br><font size=2 face="Arial">We have a release strategy which is an exact duplicate of the main one. Since, the workflow is not smart enough, to know which level the Requisition needs to be, we start over with a new strategy. Thus any &quot;significant change&quot; essentially causes a new release strategy to be looked at (Lets say one is X1 other one is Z1 with same release steps).</font>
<br>
<br><font size=2 face="Arial">There are other ways to handle this also.<br>
</font><font size=3 face="Times New Roman"><br>
</font><font size=2 face="Times New Roman"><b><br>
Regards / Mit freundlichen Grüßen</b></font><font size=3 face="Times New Roman"> </font><font size=2 face="Times New Roman"><b><br>
Vineet Mehta</b></font><font size=3 face="Times New Roman"> </font><font size=2 face="Times New Roman"><b><br>
Mercedes-Benz U.S. International, Inc</b></font><font size=3 face="Times New Roman"> </font><font size=2 face="Times New Roman"><b><br>
Phone: 205-462-5482</b></font><font size=3 face="Times New Roman"> </font>
<br>
<br>
<br>
<table width=100%>
<tr valign=top>
<td>
<td><font size=1 face="sans-serif"><b>jerry.martinek@shawbiz.ca</b></font>
<br><font size=1 face="sans-serif">Sent by: sap-wug-bounces@mit.edu</font>
<p><font size=1 face="sans-serif">10/07/2005 08:46 AM</font>
<br><font size=1 face="sans-serif">Please respond to sap-wug</font>
<br>
<td><font size=1 face="Arial">&nbsp; &nbsp; &nbsp; &nbsp; </font>
<br><font size=1 face="sans-serif">&nbsp; &nbsp; &nbsp; &nbsp; To: &nbsp; &nbsp; &nbsp; &nbsp;sap-wug@mit.edu</font>
<br><font size=1 face="sans-serif">&nbsp; &nbsp; &nbsp; &nbsp; cc: &nbsp; &nbsp; &nbsp; &nbsp;</font>
<br><font size=1 face="sans-serif">&nbsp; &nbsp; &nbsp; &nbsp; Subject: &nbsp; &nbsp; &nbsp; &nbsp;</font><font size=1 face="Arial">Purchase Requisition Workflow</font></table>
<br>
<br>
<br><font size=2 face="Courier New">Hi,<br>
<br>
We are trying to implement a one step purchase requisition workflow using<br>
BUS2009.<br>
<br>
Once the requisition is changed after it's been rejected, no events are<br>
being raised to trigger the restart of the subsequent approval process. Our<br>
functional consultant is telling me that there is nothing he can do in the<br>
release strategy setup and supposedly according to him it's a workflow<br>
problem because the changed requisition is assigned the correct release<br>
strategy.<br>
<br>
Can someone please explain what needs to be set (config/ABAP/workflow) to<br>
restart the approval workflow for a changed requisition?<br>
<br>
Thanks,<br>
Jerry Martinek<br>
<br>