Easiest way to tell if single step task and not a task in WF?
Kjetil Kilhavn
kjetil.kilhavn at bluec.no
Wed Sep 12 07:27:20 EDT 2012
Fredag 7. september 2012 12.53.20 skrev Sample, Rick:
> Hi all,
>
> Doing some archiving, cleanup, etc.
>
> Looking for the quickest way to tell if a task is a single step task and NOT
> part of a WF?
<header>-top_wi_id EQ <header>-wi_id AND <header>-wi_type NE 'F'
> If SWWWIHEAD-PARENT_WI = NULL, then this is in fact a simple
> task? Like an IDOC task, etc.?
>
> Rick
--
Kjetil Kilhavn (+47 40220607) - Blue Consulting AS (http://www.bluec.no)
More information about the SAP-WUG